Phase2
5,2 MW Phase 2    

 

   
11 x Huawei SUN 2000 60 KTL                                                    Phase2                                       
1,980 x Seraphim 440 Wp Mono
110 Strings
Pulled 55,000 Meter DC Cable 4 mm2 & 6 mm2                                    
Pulled 600 Meter AC Cable 1 C 240 mm2              
Pulled 100 Meter Grounding Cable 1 C 180 mm2                                  
Installed AC Cable Ladders 
Installed DC Cable Trays
Installed Data Cable & Solar Log
Responsible for Project Management
Produced all neccesary drawings for execution off the project
   
  ___________________________________________________________________________________________________
   
  Phase2      Phase2       Phase2      Phase   
 
 
 
 
 
  ___________________________________________________________________________________________________ 
   
 

Phase2      Phase2       Phase2      Phase2

 
 
 
 
 
  ___________________________________________________________________________________________________ 
   
  Phase      Phase2       Phase2      Phase2    
 
 
 
 
 
  ___________________________________________________________________________________________________ 
   
  Phase2       Phase2       Phase2       Phase2       Phase2
 
 
 
 
 
  ___________________________________________________________________________________________________ 
   
  Phase2               Phase2               Phase2       
 
 
 
 
 
  ___________________________________________________________________________________________________ 
   
  Phase2        Phase2        Phase2        Phase2        Phase2
 
 
 
 
 
  ___________________________________________________________________________________________________ 
   
  Phase2        Phase2          Phase2          Phase2
 
 
 
 
 
  ___________________________________________________________________________________________________
   
  Phase2       Phase2        Phase2       Phase2
 
 
 
 
 
  ___________________________________________________________________________________________________
   
  Phase2      Phase2       Phase2
 
 
 
 
 
  ___________________________________________________________________________________________________ 
   
                    Contact us  
                    Homepage Phase 2  
                    Home Page 5,2 MW Project  
                    Jump directly to Phase 1  
                    Jump directly to Phase 3  
                    Home  
   
 

Opening Hours

30 days a month we are ready to serve our customers.             

  
Monday - Friday 09:00 am – 17:00 am
Saturday   09:00 am – 12:00 noon

Contact Us 

Mobile +62 856-4527-9818 
Office +62 31 5116 1496

 

Office Location

Feel free to contact us if you have any questions.

Surabaya:

Puri Safira Regency

Cluster De Armilla block D 8 Nr 14

Jalan Raya Menganti Kecamatan Menganti-Gresik

61174 East Java Indonesia

Contact Us